NSW approvals for a granny flat

Two public paths: a complying development certificate, or a development application. Which one you are on depends on the lot, not on how keen the builder is.

The dwelling you are actually applying for

The NSW Planning Portal describes a secondary dwelling as self-contained, on the same lot as the principal dwelling, and either within it, attached to it, or separate from it. It is an extra dwelling entitlement on one parcel. If the plan is to strata or Torrens-title it off, you are describing a different project. A BASIX certificate is part of documenting a new dwelling. The Portal’s BASIX notes are the place to start, not a salesperson’s floor plan.

Complying development

Section 54 of the State Environmental Planning Policy (Housing) 2021, as consolidated on AustLII, says development for a secondary dwelling can be complying development when it is on land in a residential zone other than Zone R5 Large Lot Residential, it is not a basement or a roof terrace, it meets the general CDC rules in the Codes SEPP, it is not on land the Codes SEPP excludes, the lot is at least 450 m², and it meets Schedule 1.

Schedule 1, in that same consolidation, includes standards you should read on the lot survey rather than from memory:

  • One principal dwelling and one secondary dwelling on the lot at the end of the work.
  • A road frontage of at least 12 m on lots from 450 m² to 900 m², 15 m up to 1,500 m², and 18 m above that. Battle-axe lots have their own access test, including a 3 m handle and a 12 m by 12 m pad excluding the handle.
  • Lawful access to a public road. The schedule does not require extra parking for the secondary dwelling.
  • Site coverage limits of 50%, 40% or 30% depending on lot size, with stated exclusions for eaves, driveways, pools and open decks.
  • Floor area of the secondary dwelling, excluding an attached ancillary structure, not more than 60 m², unless another environmental planning instrument allows more.
  • A cap on the combined floor area of the principal dwelling, the secondary dwelling and attached ancillary structures: 330 m², 380 m² or 430 m² across the published lot bands.

Schedule 1 also sets height, setbacks, privacy and landscaping. Those numbers are easy to paraphrase wrongly, so they are not repeated here. Open the schedule with your survey in hand.

Sources: Housing SEPP section 54 (AustLII) · Schedule 1 (AustLII) · NSW Planning Portal. TODO: confirm these clause numbers on the in-force HTML at legislation.nsw.gov.au.

When people leave the CDC path

A development application is the ordinary path when the standards are missed or the land is excluded. The suburbs where that happens most often in this directory are the Inner West, Waverley, Mosman, the Blue Mountains and bushfire-mapped parts of the Northern Beaches, Hornsby and the Shire. Hawkesbury acreage is often in R5 or a rural zone, which is outside the CDC division summarised above.

Bushfire-prone land is a frequent reason complying development is unavailable. The Rural Fire Service publishes the mapping and the construction response. TODO: do not print a BAL cutoff on this page until it has been checked against the current Codes SEPP. Link the certificate, not a suburb stereotype.

Private covenants and estate design guidelines are a third document. They are common in Camden, new Blacktown releases and parts of the Hills. A CDC does not erase a covenant.

Flood planning can force a floor level that then fails a CDC height or setback standard. That is a design problem to find before the deposit, in Parramatta, Penrith and the Hawkesbury floodplain especially.

After the approval

A CDC can be issued by a registered certifier or a council. A DA is decided by the council. Either way you need a principal certifier, inspections, and an occupation certificate before anyone lives there. BASIX sits with the approval documents for a new dwelling.

The builder who signs the contract needs a current NSW contractor licence for residential building work above the statutory threshold. The public guidance says that threshold is more than A$5,000 in labour and materials including GST. Check it on the NSW Government licence page, and check the number you are given. Example listings on this site use an EXAMPLE prefix because they are not licensed businesses.

Home building compensation cover applies above a statutory contract value. TODO: confirm the current dollar figure on the icare Home Building Compensation pages before stating it as a fact in an ad. Do not pay a large deposit against a certificate that names a different property.

A short list before you pay for drawings

  1. Section 10.7 planning certificate from the council.
  2. Zone, lot area, frontage and whether a secondary dwelling already exists.
  3. Bushfire, flood, heritage and acid-sulfate or contamination notations.
  4. Survey, sewer diagram and a soil test if you are pricing footings.
  5. Any covenant or estate guideline.
  6. A decision, written down, about CDC versus DA. The cost guide explains why that decision belongs in the budget.

Questions

What is a granny flat in NSW planning law?

The Planning Portal describes a secondary dwelling as a self-contained dwelling established with another dwelling (the principal dwelling), on the same lot, and located within, attached to, or separate from that principal dwelling. 'Granny flat' is the ordinary name. The instrument uses 'secondary dwelling'.

When is a CDC enough?

The Housing SEPP makes some secondary dwellings complying development if the land is in a residential zone other than R5, the lot is at least 450 m², listed land exclusions do not apply, and the development standards in Schedule 1 are met. That is a summary of the consolidation widely published on AustLII. The in-force text on the NSW legislation site controls if they differ.

When do I need a development application?

When the proposal is not complying development. Common reasons include the zone, a lot under 450 m², bushfire or other sensitive land, heritage, a design that misses setback, height or site-coverage standards, or a covenant the CDC does not override. Council assesses a DA against the LEP and DCP.

Can I subdivide the granny flat onto its own title?

A secondary dwelling does not, by itself, create a second title. Subdivision is a different application and is often prohibited or refused. Do not buy a block, or brief a builder, on the assumption the backyard can be sold off.

Is this legal advice?

No. It is general information to help you read the official sources. Controls are amended. A certifier, the council, or a planner looking at your title can tell you what applies to the lot. This page cannot.

Official starting points: planningportal.nsw.gov.au, NSW Rural Fire Service, and your council’s website from the relevant suburb guide.